• FUTURE
  • 2028
    Snowy 2.0 project expected completion

    2027
    First power expected from Snowy 2.0

    BEYOND 2023
    Construction continues on Snowy 2.0

  • 2022
  • Second tunnel excavated for Snowy 2.0

    The Snowy 2.0 pumped-hydro mega project has achieved another important construction milestone, with a second tunnel excavation completed at Lobs Hole in the Snowy Mountains.

  • Milestone first tunnel excavation completed

    Snowy Hydro is celebrating the completion of excavation for its first tunnel for Snowy 2.0, with the Lady Eileen Hudson tunnel boring machine (TBM) reaching the location of the new underground power station cavern.

  • TBM Florence community event

    On 22 March, the local community came together to celebrate the commissioning of tunnel boring machine (TBM) Florence.

  • Tantangara works

    Good progress continues to be made at Tantangara (eastern end of the Snowy 2.0 project), with the headrace tunnel adit and tunnel boring machine cradle almost complete.

  • 2021
  • TBM Kirsten commissioning

    On 3 December 2021, we commissioned our second tunnel boring machine (TBM), Kirsten.

  • Manufacturing of segments

    At the Polo Flat segment factory – which will produce more than 130,000 seven-tonne concrete segments to line the Snowy 2.0 tunnels.

  • TBMs named

    We are excited to announce the winning names for our final two tunnel boring machines (TBMs) – Kirsten and Florence.

  • Tunnelling

    Our first tunnel boring machine, the Lady Eileen Hudson, is on the move.

  • Joule Ridge accommodation

    Construction is now underway for a 126-bed accommodation development in Cooma to house Snowy 2.0 workers.

  • 2020
  • TUNNELLING EXPECTED TO COMMENCE

    Main Access Tunnel excavation by TBM

  • TUNNEL SEGMENT MANUFACTURING EXPECTED TO COMMENCE

    First tunnel segments produced at Polo Flat factory

  • TUNNEL BORING MACHINES

    First Snowy 2.0 TBM arrives onsite

  • ESTABLISHMENT OF CONSTRUCTION POWER

    The Lobs Hole substation is being built to power all construction activities and the TBMs

  • MAIN WORKS PLANNING APPROVAL GRANTED

    Planning approval received from both State and Federal Government and work continues full steam ahead!

  • CONSTRUCTION OF SEGMENT FACTORY UNDERWAY

    130,500 concrete tunnel segments to be manufactured at Polo Flat, Cooma

  • SITE WORKS PROGRESS

    Construction of permanent bridges, main access tunnel portal and temporary accommodation camps; 300 people working onsite

  • 2019
  • PRINCIPAL CONTRACTOR APPOINTED

    Future Generation Joint Venture appointed by Snowy Hydro

  • Project construction commenced

    Access road upgrades and early works underway at Lobs Hole

  • EXPLORATORY WORKS APPROVED

    Approval received from the NSW Government

  • 2018
  • FINAL INVESTMENT DECISION

    Snowy Hydro Board approved a final investment decision to proceed with Snowy 2.0 and releases the FID report

  • CSSI DECLARATION

    Snowy 2.0 declared Critical State Significant Infrastructure by NSW government

  • 2017
  • FEASIBILITY STUDY PUBLICLY RELEASED

    Confirms project is technically and financially feasible

  • GEOTECHNICAL INVESTIGATION PROGRAM

    Core hole drilling program to collect geological samples and data on the rock types across the Snowy 2.0 alignment to inform the feasibility study

  • FEASIBILITY STUDY COMMENCED

    Development of the Snowy 2.0 business case, expert independent economic modelling, engineering designs and construction planning

  • SNOWY 2.0 ANNOUNCED

    Major pumped-hydro expansion of the Snowy Scheme

  • 1966
  • LETTER FROM WILLIAM HUDSON

    Original proposal to the government for pumped-storage

  • 1948
  • NEWSLETTER

    Snowy Scheme proposal

Sign up for the latest updates

Sign up